A public open house was held recently at the Dillon High School library about Dominion’s Transco to Charleston project.
This is the line that will serve Wyman-Gordon.
The purpose of the open house was to explain and answer questions about the project and the environmental review process.
Dominion Carolina Gas Transmission, LLC (DCG) has announced its intention to construct and operate 55 miles of new 12-inch diameter natural gas pipeline (Moore to Chappells Pipeline) and 5 miles of 4-inch diameter natural gas pipeline (Dillon Pipeline), along with mainline valves and pig launcher/receiver sites.
The Transco to Charleston Project (Project) would also include a new measurement station at the terminus of the Dillon Pipeline, upgrades to the Moore Compressor Station (CS), a new compressor station (Dorchester CS) about two miles northeast of St. George, South Carolina, and upgrades to the Charleston Town Border Station.
The Dorchester CS would be equipped with three 1,050 hp centrifugal turbine-drive compressor units relocated from DCG’s Southern CS in Aiken County, South Carolina.
According to a fact sheet presented at the meeting, the following is the pertinent information:
Dominion Carolina Gas Transmission proposes to construct and/or modify and operate the Transco to Charleston Project, consisting of the following facilities:
-Moore to Chappells Pipeline
-Dillon Pipeline
-Moore Compressor Station
-Dorchester Compressor Station
-Southern Compressor Station
-Charleston Town Border Station
The purpose of the project is to help meet the growing need for cleaner, reliable, domestic natural gas in the region. The component projects, shown on the adjacent map, are summarized under the Proposed Project Facilities caption to the right.
Dominion Carolina Gas Transmission is an interstate natural gas transportation company that delivers natural gas to wholesale and direct industrial customers throughout South Carolina, operating approximately 1,500 miles of transmission pipeline in South Carolina and Georgia.
These steel lines are between 2 and 24 inches in diameter and operate at pressures up to 1200psi to transport natural gas from other pipelines to local utility companies and major industrial facilities. Dominion Carolina Gas Transmission is regulated by the Federal Energy Regulatory Commission (FERC).
*
Proposed Project Schedule
Milestone—Target
Begin Land and Environmental Surveys-April 2015
Submit FERC Pre-Filing Request-July 2015
Submit FERC Filing- January 2016
Receive FERC Approval-November 2016
Begin Construction-January 2017
Project In-Service-November 2017
For public comments or questions, call (844) 296-9300. More information can be found at www.dom.com/t2c.
The Transco to Charleston Project will include approximately 60 miles of pipeline including two new natural gas transmission pipelines, upgrades to an existing compressor station, and the addition of a new compressor station. The following specifications are preliminary pending final design:
Moore to Chappells
Pipeline
-Approximately 55 miles of new 12-inch diameter natural gas pipeline
-Main line valves
-Launcher station
-Receiver station
Dillon Pipeline
-Approximately 5 miles of new 4-inch diameter natural gas pipeline
-Caldwell Drive measurement station
Moore Compressor
Station (existing)
-Install two new 1,400 horsepower compressor units
-Install additional gas cooling units
Dorchester Compressor
Station (new)
-Construct a new compressor station with three, 1,050 horsepower compressor units
Southern Compressor
Station
-Remove three 1,050 horsepower compressor units
-Convert one 1,050 horsepower compressor unit from standby to baseload service.
Charleston Town Border
Station
-Install an overpressure protection system and controls